Corrievarkie Pumped Storage Hydro Project    

LIVE MEETINGS
19th May 7pm - 9pm

Play Video

We are looking to engage with the local community in advance of submitting a Scoping Report to the Energy Consents Unit (Scottish Government). This will enable people to find out more about the proposal and raise any questions or queries they may have. We will be hosting an online live presentation where viewers will be able to ask questions through the website and provide comments by filling out an online comment form.

Comments made to ILI Group are not formal representations. If we submit a planning application, there will be an opportunity to make formal representations on the application. A further, formal public event would also be held in advance of a planning application.

There will be a project website launching soon at www.corrievarkiepsh.co.uk

Ask us a question...
Greig Templeton - ILI
Hello. I am Greig Templeton, the Planning Project Manager for ILI Group. Please use this chat box feature to ask questions. You can asked questions at any point and we will answer these at the end of the presentation.
Greig Templeton - ILI
It would be helpful if you could also just say a quick "hello" and let us know you are here.
Greig Templeton - ILI
Welcome. Our presentation will start in a few minutes.
visitor769
Hello, i am Kees van Well
Greig Templeton - ILI
Hello. Welcome. The presentation is about to start.
Greig Templeton - ILI
You may have to press the "play" icon to see and hear the presentation. If so, you may run a few minutes behind but don't worry. I am live here and will pass on any questions and comments you may have.
visitor769
thxs but i receive you well
Greig Templeton - ILI
Feel free to put any questions you have here and we will answer them at the end. Alternatively if you want to ask a question in confidence you can email Ross and he will reply via email. His address is rm@ili-energy.com
visitor771
As the chair person of Dalwhinnie Community Council we are interested to know the full extent of disruption fir the village and particularly the are on the map, A889, station road through to Ben alder road as it seems to run straight through homes of Ben Alder Road in a field owned by a local estate, ardverikie?
visitor771
Dalwhinnie is part of highland council not just Perth and Kinross, therefore will highland council also be consulted otherwise Dalwhinnie community council will not be included in planning applications or developments?
visitor771
Will you allow this presentation to be emailed out to community councils ASAP so all members can see the information clearly at CC meetings?
visitor772
What will be the level of daily construction traffic be on the access track to the south, more so once the road has been upgraded and construction work is focused on the main head pond and tunnelling site.
visitor771
Please do contact us when you are scoping boundaries and looking at new road access as we will engage as positively as possible if it is to the benefit of the village! And thanks for answering my questions - very much appreciated
Greig Templeton - ILI
If you joined after the presentation ended you can watch it again on this webpage. Please click the "play" button. This will be available here for at least 4 weeks. Please feel free to get in touch with us and we would encourage you to use the feedback sheet at the bottom of the page. Thank you for your time this evening and we hope to see you all in person soon.
Add Name

If you cannot see the chat box please text any questions to 07861667903

What is the project

Who are ILI Group?

Why is it needed?

Why in this Location?

Location Plan

Site Layout

Energy Storage Units

Substation

Fencing